medical waste incinerator: medical waste and general waste
Capacity to burn waste: 400 — 500 kg/hr
Fuel: Diesel
Fuel Consumption: 10 litres/hr maximum
Incineration temperature: 950 – 1300 °c
Casing: thick (min 5 mm) Stainless steel casing and fully
insulated to withstand sea humidity
Voltage: 220/240 V or 380/415V
Frequency: 50 Hz
Feeding: automatic
Ash 1 leftovers removal: Automatic
Fuel gas filtration system: Yes
Warranty: 12 months
Staff training: Operator & Maintenance staff
Operation and service manuals: 3 sets each
Especifica??es Gerais 6 mm plate steel sheel construction
11cm 1400°C refractory Liner
temperature controlled Burners
secondary combustion burners
interlock switch on load doors
separete ash door
one secondary residence @ 1000°C
400°C silicone Based finish paint
alloy temperature sensor
factory wired and tested
Capacity 20kg/hr
primary Chamber 1607 L
Hearth area 1.36 aq.m
Secondary Chamber 694L
Primary burner (oil) 420.00btu
Secondary burner (oil) 900,000btu
Secondary combustion 1/6 hp
Exhaust stack 46cm x 6m
Electrical service 220/50
System weight 5,700kg
Dimension “D” 152cm
Doad port height e 60x60cm
Ash port height e 36x36cm
General Specifications 6mm plate steel sheel construction
11cm 1400 ° C refractory liner
temperature controlled Burners
secondary combustion burners
interlock switch on load doors
separete ash door
one secondary residence @ 1000 ° C
400 ° C silicone based paint finish
alloy temperature sensor
factory wired and tested
Capacity 20kg/hr
primary Chamber 1607 L
Hearth area 1:36 aq.m
Secondary Chamber 694L
Primary burner (oil) 420.00btu
Secondary burner (oil) 900,000 btu
Secondary combustion 1/6 hp
Exhaust stack 46cm x 6m
Electrical service 220/50
System weight 5.700 kg
Dimension “D” 152cm
Doad port height and 60x60cm
Ash port height and 36x36cm
medical, hospital, veterinary and industrial wastes by medical waste incinerator Process.
So, we’re interested with your Incinerator plants, and we’d like to get quotation and key features description of different capacities of your Incinerator plants, concerning: small models (5 – 25 kg/hr); medium models (25-50 kg/hr) and big models (50-100 kg/hr) and plus.
Jul, 2025
medical waste burners suppliers
chemical representatives to be made use of:
10% heptyl (unsymmetrical dimethylhydrazine) water solution,
heptyl (unsymmetrical dimethylhydrazine) vapour with 0.8 to 1.0 kg/m3 concentration,
10% azotic (nitric) acid water remedy,
azotic (nitric) acid vapour with focus up to 1.1 kg/m3;
2. neutralization approach: thermal decay;
3. neutralization temperature level: +800? C to +1200? C;
4. performance:
? vapour ability: 70 to 200 m3/h,
? water option ability: 50 to 500 l/h;
5. inlet stress: as much as 2 bars;
6. automatic control system;
7. total measurements shall allow for placing the unit on a car framework.
clinical waste burners producers General Specs
6mm plate steel sheel construction
11cm 1400 o C Refractory L iner
Temperature regulated Heaters
Additional combustion Heaters
Interlock Turn On Load Doors
Separate Ash Door
One 2nd secondary Home @ 1000 o C.
400 ° C Silicone Based Paint Complete.
Alloy Temperature Sensing Unit.
Factory wired as well as examined.
Capacity-20 kg/ human resources.
Primary Chamber-1607 L.
Hearth Area-1:36 sq. m.
Second Chamber-694 L.
Primary Burner (oil) -420,000 btu.
Secondary Heater (oil) -900,000 btu.
secondary Combustion-1/ 6 hp.
Exhaust Stack-46cm x 6m.
Electrical Service-220/ 50.
Weight System-5.700 kg.
Measurement “D” -152 cm.
Tons Port Elevation- 60x 60 cm.
Ash Port Elevation -36 x 36 cm
Jul, 2025
health center incinerator manufacturers
The Incinerator Plant is outcome wastes incineration from Different petrochemical devices. In this job we wish to blaze all output wastes from petrochemical devices and additionally created high pressure steam from burner plant warmth created.
In the beginning outcome waste from petrochemical collects and also moves to transit and also arranging facility in various types. Input feeds of burner plant are received below table:
health center incinerator suppliers, Waste streams of petrochemical unit collect and also keep en route and Arranging Facility.
En Route and Arranging Center one laboratory need to be considered.
In this facility, waste will be identified in 2 groups:
–– Improper for burning
–– Appropriate for burning
Unsuitable waste for burning can be separated into the 4 classifications:
–– Buried materials
–– Materials (wastes) that require to be stabilized prior to hidden
–– Materials (wastes) that can be offered.
–– Wastes that can be gone back to petrochemical.
Appropriate wastes are identified right into both classifications:
–– Input wastes to rotating kiln, contain solids and also waste liquids.
–– Input wastes to fixed kiln, include clean fluids and also gasses.
All strong wastes must be transferred to storage space pit from Transportation as well as Sorting. Solid wastes storage space pit is input of rotary kiln.
All fluid wastes need to be kept and maintained in Transit as well as Arranging. All storage as well as stablizing tools or center have to be taken into consideration. Storage space as well as stabilization tools (facility) consist of:
Tanks, Pumps (Transfer, Loading & & Unloading), Agitator (Mixer), Blanketing System, Flare system, Instrumentation as well as Control Solution, and so on
. Storage and stablizing capacity need to be taken into consideration based on worst instance (shut down).
Typically incinerator plant contains two similar trains (capacity of each train is 100%). Each train consists of a rotary kiln as well as a fixed kiln.
Jul, 2025
chinese burner suppliers
In a simple design with a metal steel drum electric. including:
A cage for receipt of biomedical waste;
A combustion chamber with fireplace with a filter to retain ashes;
A cover;
An air supply;
A turbine allowing the supply of the air.
Combustion temperature: 1800 ° C. Compliance with European standards.
Comes with all necessary accessories
Supply of incinerator model PDR-18 with:
· Capacity 100 kg/hr of waste containing up to 85% moisture
? Two combustion chambers
· Two fully automatic, oil fired, pressure jet burners
· Panel board
· Diesel tank of capacity 250 It. with 2 diesel pipelines, filter and valve.
Type: for animals waste
Capacity: 30 kg per hours for a maximum load of 120 kg.
GLP Gas
Voltage: 110V-120V
Semiautomatic control board
Stainless steel chimney, 3.5 meters above the incinerator.
High temperature painting for all the incinerator.
Front door for loading and unloading.
Fuel Diesel Oil 8/ kerosene
Capacity (m3) 0.57
Ave Capacity 50 kg per hour
Ave time for Burnout 5 hrs
External Dimensions
Length 2000mm
Width 1100mm
Height including flue 3500mm
Door opening
Internal Dimensions
(primary chamber)
Length 1200mm
Width 620mm
Height 660mm
Operation
Min. operating temperature 9500C
Max. operating temperature 13200C
Residency time in second chamber 2.0 seconds
Weight 1850kgs
Ancillaries
Operating and maintenance manuals
Recommended Spare list
300 liter fuel tank
Plant burning rate – 100kg/hr
Fuel – Diesel oil – 35 sec Redwood
Overall dimensions are as follows:
Width 2261mm
Length 3264mm
Chimney Diameter – 390mm
Chimney Height – 8000mm
chinese incinerator manufacturers, We process 8-10 ton waste of sheep carcass and its byproduct per day. We are looking for the equipment: combustion burners(combined fuel supply:natural gas and diesel),control panel and filter system. The diameter of the incinerator is 20 cm. Lower calorific power of the waste is 4KW/KG. Heating power 4000KW
Jul, 2025
clinical waste incinerator china
medical waste incinerator china, Design, supply and manufacture ex works of one Surefire Manual Load TS50/1 Medical/General waste incinerator as detailed below: –
· Waste type: Mixed type o,1,2,3,&4 hospital/clinical bio hazard waste
· Waste density: 125 to 350Kg/M3
· Waste CV: 4000 KCAL/kg
· Moisture content: 10-25%
· Estimated ash residue: 5-10%
· Nominal capacity: 30Kg/hour batch load
· Secondary chamber: 0.5 second @ 850oC
· Compact laboratory style
· Two combustion chambers
· Ecologically friendly
· Up to 50kg of waste / hour
· To be used for animals
Jul, 2025
pet waste incinerator manufacturer
Technical requirements for burning device, animal waste incinerator supplier
1. 2 systems are called for to be mounted in the south of the Kingdom of Saudi Arabia. The two systems will be utilized by personalized authority to burn different sort of drugs. All demand devices need to be provided.
2. Warranty: booth systems need to be given with 3 years warranty from the date of approval. All required extra components, preventative upkeep repair and also restorative upkeep need to be included in the cost as well as provided to the client.
3. All required electric as well as water links should be offered.
4. Both systems have to be of premium quality and must be environmental friendly.
5. The capacity of each system must be up to 100 kg/hr.
6. The system has to have automated feeding.
7. Each system must includes two burning rooms, one main space for burning the medication and also one more space for burning the gases that emit as a result of main burning.
8. The oven should be constructed from steel that is corrosion resistance and with thickness not less than 6 mm.
9. Each system should be of high reliable in shedding various sort of medicines, and also ought to have 99.9% effectiveness for burning organic products.
10. Waste products need to not exceed 5%.
11. System needs to have automatic ignition system.
12. System needs to utilize diesel (HSD) as fuel and ought to not consume more than 8 to 10 lt/hr.
13. Each system ought to be given with fuel storage tank of dimension appropriate to run the system for one complete day.
14. The temperature level in the primary room should be 850 C ± 50 C. the system need to additionally be qualified to operate as much as 1050 C ± 50 C. the system should can continues operation as well as should be supplied with concrete layer insulator with appropriate density.
15. Oven should be provided with warm insulator to permit easy operation.
16. Gas ought to stay in the additional area for not greater than 1.5 second.
17. The main burning area must contend least 2 heaters.
18. The second burning area need to have one heater.
19. Each system must have doors for ash, leave for air to the smokeshaft and also windows to allow looking inside and for maintenance.
20. Each system must have filtering system for gas handling with 2 tanks utilizing average water. Each water container must have capability of 1000 lt and ought to be repaired to the system as well as offered with water degree indication.
21. Each system must have special innovation for separating midsection products and also humidity after gas processing.
22. Each system needs to have cooling down ability after procedure.
23. Each system m must be offered with exhaust pipe with 250 mm diameter and also 10 m high. The base of the exhaust system ought to be 1000 mm. The exhaust pipe must be 6 mm as well as needs to be supply with heat insulator. The exhaust system should be provided with pressure sign. It ought to additionally offer with ladder and Lightning Arrestor.
24. Electric power: need to be 220 volt, 3 phase, 60 Hz, as well as the motor must not be less than 15 HP.
25. Each system must be given with control panel and also indicators and needed security devices and alarm. The control panel ought to reveal at least temperature level in both the key and additional areas and also injectors of the filters and also load.
26. Each system ought to be offered with security system for any break down or defect of any type of part of the system.
27. The complying with personal protective tools have to be provide:
a.Heat immune garments for 20 individuals.
b.Heat resistant goggles for 20 persons.
28. All elements of each system must be repainted with silver color that is heat resistant.
Jul, 2025
affordable incinerators
RECYCLABLE WASTE PLASTIC (NON-PVC) 218,693
CARDBOARD 85,046
PAPER 4,956
PVC 15,115
HAZARDOUS WASTE MEDICAL WASTE 1,084
SOLID WASTE CONTAMINATED WITH HYDROCARBONS 300,680
USED ENGINE OIL FILTERS 85,423
HYDROCARBON-CONTAMINATED DIRTS 88,680
COMMON WASTE FIBERS 14,078
USED AIR FILTERS (AUTOMOTIVE AND ALSO SIMILAR) 23,149
INDIVIDUAL PROTECTIVE DEVICES (PPE), INCLUDING INFECTED CLOTHING AND ALSO SIMILAR PARTICLES 130,861
Pig corpses/ roaming pet dogs and also bigger pet carcasses economical incinerators ––.
Lots ability in the variety of up to 300 kg/ Melt rate approx. 50 kg per hour
Temperature Controlled Heater. Burners to be made to meet the Norms of Pollution Control. Modern technology: Heavy-duty covering, to be a top quality, rugged, dependable, affordable Burner with pertinent control, very easy to operate and also self-supporting. Systems to be pre-assembled, pre-piped, pre-wired & & examined prior to Transport/ Export.
Note: Comparable Modern Technology and/ or Tenderers Proposals rate.
Within the structure of an ecological tools & & technology consultation and joint buying, this Procurement/ Notary Bureau welcomes candidates for pre-qualification in the purpose of largely choosing qualified companies to bid for the above tender.
The supply will make up the special devices for efficient waste monitoring as pointed out above for a brand-new personal setting contract management firm with prepared procedures 2013 in Indonesia as well as Thailand, as well as 2015 in West & & East Malaysia to execute those expert services in order to follow the federal governments safety disposal requirements for animal waste in the region as well as to satisfy the higher technical standard in this specific area in order to secure the public and consist of infectious & & contagious infections and also pet triggered conditions. The spread of a brand-new illness of pigs, likewise the ‘‘ Nipah Infection Illness’, first noticeable in 1998 in S.E.Asia, which causes illness and also fatality in both humans as well as pigs, is on the rise once again; as well as the premature death of plants and also boars was recorded in pig farms in Malaysia as well as other locations in S.E. Asia.
Jul, 2025
waste burner maker china
waste incinerator producer china, Waste chamber
Chamber capacity 300 kg
Chamber volume.54 m3.
Chamber size (exterior) Size: 91cm, Elevation: 86cm Length: 152cm.
Door opening 66 x 76 cm.
Elevation to door 84 centimeters.
Height to top of stack 5.4 m.
Suggested slab size (L x W x Thickness) 1.8 m x 2.4 m x 10 centimeters.
Shed price: About 45 kg/hr.
Stack:.
2′′ -14 ″” dia.( 36 cm), 14 scale (1.90 mm) aluminized steel, refractory lined.
8′′ -12″″ “dia.( 30.5 cm), 16 scale (1.52″″.
” Burners Diesel.
Operation Manual timer.
Electric solution Requirement – – 115 volt, 60 HZ, 20 amp.
General Description:.
Primary Chamber: Sturdy steel covering.
Top quality refractory cellular lining and insulation.
Huge complete dimension top tons door as well as liquid retention sill.
1 x diesel oil terminated ignition heaters operated on/off.
Ash removal door.
Chimney: Durable stainless steel housing.
1.5 m size.
0.6 m refractory lined stack.
Control Panel: Control of 1 heater.
Timer control 0-12 hours.
Indispensable follower timer control.
Temperature surveillance.
Automatic Control.
Cycle time set up.
Ancillaries: Operating and upkeep handbooks.
Spares list.
Ash Rake.
Containerization: 20 foot shipping container with incinerator fitted.
500 litre gas storage tank
Jul, 2025
china medical burner
the following containerized burners. (Kitchen area and lodging and grey water and black water plant eliminating waste) we need burner is each function different are done in one burner we need notified. Plant we installing for our holiday accommodation barge made use of in an offshore marine building and construction project. 200 Individuals would certainly be fit onboard.
WASTE BURNERS RECOMMENDATIONS
china medical incinerator Capability
? Blaze minimal 80kg/hr X 12 humans resources per day
? Disposal of both non-hazardous and contaminated materials streams (per waste inventory).
? Mobile System (Skid installed preference with lifting factors).
Design/Specifications.
? Incinerators must have an additional combustion chamber with a minimum temperature variety of 900c.
? Fluid waste streams shall be incinerated by a proper fluid injection system.
? The burners will certainly be mounted with visual alarms to signal procedures of low temperature in the secondary chamber.
Running Environment and also Ambient Problems
The Incinerators plan shall be developed to operate under the following conditions:.
? Ordinary Daily Max/Min June Temperature Level, 21-39 ° C.? Ordinary Daily Max/Min January Temperature Level, 2-12 ° C.
Medical waste burner,.
approx. 0.4 cubic metres,.
gasoline/ keys power operated,.
thermostatic temperature level control,.
programmable cycle
Jul, 2025
small capacity burners
1 Basic Plant Design An approved plant must have four distinct sections that demonstrate three principles of Turbulence, Residence Time and Temperature are inbuilt in the plant design .The regulated sections may include but not limited to:
Overall plant layout.
Feed chamber/ charging
Primary Combustion Chamber.
Secondary Combustion Chamber.
Particulate Scrubbers
Acid Gas Scrubbers
The stack/ chimney.
2 Feeding And Charging Controlled hygienic, mechanical or automatic feeding methods have to be used which will not influence the air temperature in the primary and secondary chambers of the incinerator negatively.
No waste is to be fed into the incinerator:
1. Until the minimum temperatures have been reached.
2. If the minimum combustion temperatures are not maintained.
3. Whenever the previous charge has not been completely combusted in the case of batch feeding.
4. Until such time as the addition of more waste will not cause the design parameters of the incinerator to be exceeded.
3 Primary Combustion Chamber The primary combustion chamber must:
1. Be accepted as the primary combustion zone.
2. Be equipped with a burner/s burning gas/fuel or low sulphur liquid fuels. Other combustion methods will be judged on merits.
3. Ensure primary air supply is controlled efficiently
4. Ensure minimum exit temperature is not less than 850oC
4 Secondary Combustion Chamber (Afterburner). The secondary combustion chamber must:
1. Be accepted as secondary combustion zone.
2. Be fitted with secondary burner/s burning gas or low sulphur liquid fuel or any suitable fuel.
3. Ensure secondary air supply is controlled efficiently.
4. Ensure flame contact with all gases is achieved.
5. Ensure residence time is not less than two (2) seconds.
6. Ensure the gas temperature as measured against the inside wall in the secondary chamber & not in the flame zone, is not less than 1100oC.
7. Ensure the oxygen content of the emitted gases is not less than 11%.
8. Ensure both primary and the combustion temperatures are maintained until all waste has been completely combusted
5 Particulate Removers A mechanical particulate collector must be incorporated after secondary combustion chamber for removal of particulate pollutants entrained in the flue gas stream. The particulate collectors may include any of the following or a combination thereof:
Cyclone separator
Electrostatic precipitators
Fabric filters
6 Chimney / Stack 1. The chimney should have a minimum height of 10 meters above ground level and clear the highest point of the building by not less than 3 meters for all roofs. The topography and height of adjacent buildings within 50 meters radius should be taken into account.
2. If possible the chimney should be visible to the operator from the feeding area.
3. The addition of dilution air after combustion in order to achieve the requirement of these guidelines is unacceptable.
4. The minimum exit velocity should be 10 m/s and at least twice the surrounding wind speed (Efflux velocity = wind speed x 2) whichever is higher to ensure no down washing of exiting gases.
5. Point for the measurement of emissions shall be provided.
7 Instrumentation Instrument for determining the inside wall temperature and not burner flame temperature must be provided for both primary and secondary chambers.
2. An audible and visible alarm must be installed to warn the operator when the secondary temperature drops to below the required temperature.
3. In addition to the above the following instruments may also be required.
A carbon monoxide and/or oxygen meter/recorder
A smoke density meter/recorder
A gas flow meter/recorder
A solid particulate meter/recorder
Any other instrument or measurement that may be considered necessary
8 Location / Siting 1. Must be sited in accordance with the relevant local municipal authority planning scheme, the topography of the area and be compatible with premises in the neighborhood,
2. Must be housed in a suitably ventilated room.
9 Emission Limits 1. Combustion efficiency:
Combustion efficiency (CE) shall be at least 99.00%
The Combustion efficiency is computed as follows;
C.E= % CO2 x 100
% CO2 + CO
2. The temperature of the primary chamber shall be 800 ± 50o C
3. The secondary chamber gas residence time shall be at least 1 (one) second at 1050 ± 50o C, with 3% Oxygen in the stack gas.
4 Opacity of the smoke must not exceed 20% Viewed from 50 meters with naked eyes
5. All the emission to the air other than steam or water vapour must be odourless and free from mist, fume and droplets.
6. The Authority may require that the certificate holder have tests carried out by an accredited institution to determine stack and/or ground level concentrations of the following substances.
Cadmium and compounds as Cd
Mercury Hg
Thallium Tl
Chromium Cr
Beryllium Be
Arsenic As
Antimony Sb
Barium Ba
Lead Pb
Silver Ag
Cobalt Co
Copper Cu
Manganese Mn
Tin Sn
Vanadium V
Nickel Ni
Hydrochloric HCL
Hydrofluoric acid HF
Sulphur dioxide S02
7. A 99.99% destruction and removal efficiency (DRE) for each principal organic hazardous constituent (POHC) in the waste feed where:
DRE = [(Win – Wout)/Win]*100
Where: Win = mass feed rate of the POHC in the waste stream fed to incinerator, and
Wout = mass emission rate of POHC in the stack prior to the release to the atmosphere.
8. The average dioxin and furan concentration in the emissions should not exceed 80ng/m3 total dioxins and furans if measured for a period of 6 to 16 hours.
Note:
All pollutant concentrations must be expressed at Oo C and 1.013 x 10 5 N/m2, dry gas and 11% oxygen correction.
Oxygen correction is computed as:
Es = 21 – Os x EM
21 – OM
Where: Es = Calculated emission concentration at the standard percentage oxygen concentration
EM = Measured emission concentration
Os = Standard oxygen concentration
OM = measured oxygen concentration
10 Operation 1. Materials destined for incineration should be of known origin and composition and must be only incinerated in a furnace that is registered for the particular type of waste.
2. A record must be kept of the quantity, type and origin of the waste to be incinerated.
3. The incinerator must be preheated to working temperature before charging any waste.
4. The incinerator must not be overcharged.
5. The incinerator must be in good working order at all times and must not be used if any component fails. Any malfunction should be recorded in a log book and reported to the relevant authority.
6. The incinerator operator and all relevant staff must be trained to the satisfaction of the relevant control authority.
11 Housekeeping The site where the incinerator is built must:
1. Have running water.
2. Have a solid floor.
3. Have lighting if 24hrs operation
4. Have fly ash containerization and storage before disposal.
12 Health & Safety (Protective Gear) 1. Staff handling waste must be well trained on safe handling of hazardous wastes
2. Staff must be provided with appropriate protective gear such as, gas mask, aprons, gumboots, helmets, gloves, goggles.
3. Caution and Warning signs must be provided.
4. Fire fighting equipment must be provided
5. There should be no smoking or eating on the site.